Marsh Green Primary School

Summit Projects delivered a single-storey extension to the school's occupied caretaker's house, creating the shell and services for a new open-plan kitchen and family room with associated remodelling and external works.
Location
South Close, Dagenham, Essex RM10 9NJ
Client
London Borough of Barking & Dagenham
ROLE
Principal Contractor
SECTOR
Public / Education
BEFORE WORKS
Scope of Works

The 18-week project combined demolition, new-build construction, internal remodelling and services installation to create the extended family space. The works included:

External Works & Services

The extension received new foul and surface-water drainage, gutters and downpipes, together with a contractor-designed heating and hot-water installation incorporating a new condensing combi boiler, radiators and copper distribution.

A raised patio was formed using salvaged paving, entrance paving was relaid, boundary fencing and brickwork were reinstated, and disturbed landscaping was finished with new topsoil and grass seed.

Project Delivery
Safely delivered on a live primary school site

The school remained fully operational and the caretaker’s family stayed in the house for part of the contract. Summit Projects maintained strict safeguarding controls, enhanced DBS requirements, secure separation and deliveries timed around school drop-off and collection.

The project was coordinated with the London Borough of Barking and Dagenham, Munday + Cramer, the Head Teacher and site staff, and was handed over with Building Regulations approval, guarantees and complete O&M information.